Mammoet successfully lifts five major components for Visakh refinery modernisation project

Mammoet successfully lifts five major components for Visakh refinery modernisation project
Published: 4 November 2019 - 9 a.m.
By: Martin Menachery
Mammoet contributed to the Visakh refinery modernisation project by safely and successfully completing lifting of five major components at three lifting positions at the refinery on time. Owned by a state-owned company Hindustan Petroleum Corporation Limited (HPCL), the project entails modernisation and enhancement of its refining capacity from 8.33MMTPA to 15MMTPA at a new process area on the east of its original plant. L&T Hydrocarbon Engineering has undertaken the EPC (engineering, procurement and construction) task and engaged Mammoet’s MSG80 Ring Crane, the module sliding gantry with 3,000 tonnes lifting capacity.

What makes this project unique is that the close coordination and carefully engineered lifting operation among HPCL, L&T and Mammoet made possible to overcome logistical and operational challenges without compromising safety and schedule.

Mammoet lifted five major components at three different lifting positions: two columns at Crude Distillation Unit (CDU) and Vacuum Distillation Unit (VDU), followed by three reactors and other lighter columns at Full-Conversion Hydro-Cracker Unit (FCHCU). Stage one reactor at FCHCU area weighs 1,646 tonnes, being the heaviest reactor ever installed in India. Relocation of a 3,000 tonnes class crane is already a big operation by itself. With support from L&T, Mammoet took the modularised transport approach by moving the crane in big blocks to expedite the two relocation activities.

Another ingenious solution is a 2,000Te capacity tailing frame, mounted on SPMT (self-propelled module transporter). For lifting of the stage one reactor, none of the cranes on site had a sufficient lifting capacity to function as a tailing crane for MSG80. Bringing in a heavy-duty crane just for one lift was not an economical solution on top of the fact that the site was a highly congested area with no practical space to place such a large tailing crane.

Mammoet provided good mix of the solution with a main crane strong enough to lift all the heavy items for the project, and the in-house designed tailing frame on SPMT that eliminated the need of a heavy-duty tailing crane and saved its space. This significantly improved our overall cost efficiency and productivity of the surrounding construction activity” says V Muthuraman, deputy general manager of plant and machinery, L&T Hydrocarbon Engineering.

For the latest refining and petrochemical industry related videos, subscribe to our YouTube page.